RA : Risk Management Action Plan (RMAP)



Risk Management Action Plan (RMAP)




Phase & Issues/Risk to be addressed
Recommended Actions To Be Taken
Whom
When
Design:
    OHS&E requirements not included &/or effectively integrated into design
·   Qualified/experienced OH&S construction projects manager must be engaged at commencement of this phase as an integral part of the construction project team to review site/plans & provide appropriate advice &/or guidance.
·    This is most important as it sets the OHS&E standards for the entire project duration and embeds the OH&S culture right from the get go.  + Initial formal risk assessments on all construction aspects of the project.
Project and
Safety
Department
Design
Phase.
Contractor Tendering:
·    Contractors with poor safety management history a

re engaged for work.
·    Contracts do not provide adequate clauses/detail to ensure safety compliance &/or encourage excellence in safety performance.
·    Contractor pre selection process to be formulated and implemented to screen out contractors with a history of poor safety compliance/performance.
·    Contracts to be drafted with concise OHS& E requirements & incentive/disciplinary elements clearly outlined. 
Project and
Safety
Department
Design
phase
Procurement:
·    Sub standard/unsafe equipment's critical to the maintenance of a zero harm construction work environment are provided by contractors
Appoint a corporate procurement officer to ensure quality & availability, as much of the PPE & critical equipment required for safety compliance & high risk work is procured & provided by the principle (Organization) as is possible.               
Such equipment should include but not be limited to;
·    PPE: Principle to supply safety glasses, high visibility shirts/vests, shoes, welding screens, welding masks, gas/dust masks, gloves, safety harness, safety lanyards, ear plugs/muffs, fall arrest/restraint systems (including 10mm FSWR life lines) & face shields etc.
·    Electrical: Lead stands, lighting, heat shrink cable join kits, RCD’s & cable ties etc.
·    Lifting equipment: Cranes, Slings, shackles, Man cages, hooks, shackles, pulleys & winches etc.
·    Barricades: mobile barriers & danger tape etc.
·    Scaffolds: H frame scaffold sets, 4mm pipes, couplers, clips, joiners, deck planks & base plates/sole boards etc.
·    Ground support & Machine guarding: At least 10mt of 5mm x 20mm (squares) steel grid mesh.
·    Emergency rescue (WAH): Stokes litters, rescue ropes, rescue harnesses, figure , descender’s & rescue training etc.
Project and
Safety
Department
Design
phase
Site development & workforce deployment:
·    Disruption to existing plant production schedules/operations.
·    Materials/equipment storage area’s
·   Construction workforce welfare.
·    Clearing of ground & demolition of old line works etc.
·    Design lay out of construction materials lay down storage areas, design lay out of fabrication areas, design layout of hazardous substance storage & design layout of machinery/vehicle parking/maintenance. 
·    Assessment of existing accommodation, ablutions, messing facilities & capacity site drinking water supplies/outlets to address/up grade/construct new facilities prior to deployment of the construction worksite.
·    Risk assessments on all the above.  
Project and
Safety
Department
Design phase
Civil works:
·    Survey, Excavations, concrete pads/rafts, reinforcement erection & Footings.
·    New line Building and Silo construction.
·    Slip forming concrete works.
·    Manual formworks construction & dismantling.
·    Scaffold, work platform entry/egress walkways/ramps erection/dismantling.
·   Development, establishment, enforcement & maintenance of site safety standards.
·    Development, establishment & maintenance of site safety policies, procedures, competency based training/assessment modules and compliance monitoring/controls etc.
·    Development & maintenance of OHS&E statistical analysis, compliance monitoring and reporting structures.
·    Development & delivery of formal structured training programs to address all of the above.
·    Auditing site OHS&E management performance, safe work practices compliance and continual development of OHS&E systems & resources to address identified shortfalls. 
·    Training in all FPE elements. 
Project and
Safety
Department
Senior skills
Consultant
&
Senior 
OH&S
consultant
& project team.
Civil Phase
Mechanical fabrication & erection:
·    Rigging/slinging, lifting & movement of loads.
·   Welding, cutting, grinding & painting/coatings fabrication works.
·  Transportation, lay down, storage and erection of major steel works.
·    Development, establishment, enforcement & maintenance of site safety standards.
·    Development, establishment & maintenance of site safety policies, procedures, competency based training/assessment modules and compliance monitoring/controls etc.
·    Development & maintenance of OHS&E statistical analysis, compliance monitoring and reporting structures.
·    Development & delivery of formal structured training programs to address all of the above.
·    Auditing site OHS&E management performance, safe work practices compliance and continual development of OHS&E systems & resources to address identified shortfalls.
·    Training in all FPE elements.     
 Project and
 Safety
Department
Senior skills
Consultant
&
Senior 
OH&S
consultant
& project team.
Mech Phase
Pre commissioning:
·    Transportation, lay down, storage & installation of plant machinery, power supplies, piping, electrical cabinets, and other production machinery equipment/components.
·    All FPE elements.
·    Rigging/slinging, lifting & movement of loads.
·    Installation of power, drainage, ablutions, water & fuel  services.
·    Development, establishment, enforcement & maintenance of site safety standards.
·    Development, establishment & maintenance of site safety policies, procedures, competency based training/assessment modules and compliance monitoring/controls etc.
·    Development & maintenance of OHS&E statistical analysis, compliance monitoring and reporting structures.
·    Development & delivery of formal structured training programs to address all of the above.
·    Auditing site OHS&E management performance, safe work practices compliance and continual development of OHS&E systems & resources to address identified shortfalls.
·   Training in all FPE elements.     
Project and
 Safety
Department,
Senior skills
Consultant &
Senior 
OH&S
consultant
+  Production
& project
teams.
Pre-comm
Commissioning.
Run up & test all new line components such as;
1 .Boilers/STG systems.
2 .ESP, fans, chimney’s & associated systems.
3 .Conveyor systems.
4 .Computer control systems. (DCS)
5 .System instrumentation.
6 .Electrical systems.
7 .Alarm systems.
8 .Re-claimers.
9 .Crushing & Milling units.
10. Rail &/or truck load out units.
11. Dust extraction units.
12. Compressed air delivery systems.
13. Bagging systems.
14. Silo & other bulk materials storage and handling systems.
15. Cooling towers & associated equipment's.
16. Pumping systems.
17. Kilns.
.
·   Development, establishment, enforcement & maintenance of commissioning safety standards. 
·   Development, establishment & maintenance of commissioning safety policies, procedures, and competency based training/assessment modules and compliance monitoring/controls etc.
·   Development & maintenance of OHS&E statistical analysis, compliance monitoring and reporting structures.
·   Development & delivery of formal structured training programs to address all of the above.
·   Auditing site OHS&E management performance, safe work practices compliance and continual development of OHS&E systems & resources to address identified shortfalls.
·  Training in all FPE elements. 
Project and
Safety
Department
Senior 
OH&S
consultant
+ Production
& project
team s.