Chapter :- Construction Safety
SAFETY AT DIGGING & EXCAVATION
![]() |
1. Context:
The digging and excavation of trenches is considered to be a
hazardous task due to the potential for unplanned contact with
utilities/services and the potential for injury from the collapse /localized
failure of trench walls. It is therefore critical to establish suitable risk
controls to avoid fatal injuries resulting from material instability and
inadvertent contact with underground services/utilities.
2. Purpose:
To detail the functions necessary to manage the design,
planning and work method for the excavation of openings or trenches such that
adequate safeguards are implemented to prevent contact with utilities and
exposure to loose material.
3. Scope:
This element applies to the
management of any task requiring the penetration of the ground to a depth
deeper than 300 mm. Therefore the scope is wider than simply the digging of
trenches. This element excludes bulk excavation work being performed in
quarries, stockpiles and spoil piles.
4. Element Requirements
4.1 Hazard Identification Risk Assessment and Control
![]() |
A procedure must be established for the issuing of an excavation permit. The procedure will ensure all digging and excavation work performed outside a quarry must be conducted under the authority of an excavation permit. The excavation permit must address the following key issues:
Type of work being preformed:-
- Identification of underground utilities and services including the requirement for verification by the appropriate person that the area has been checked for underground services/utilities.
- Soil type (ground conditions)– hard rock, clay, soil or sand
General safety requirements:-
- Barricading & signage
- Segregation distances or barriers between personnel and mobile equipment and/or a loose digging face
- Personal protective equipment
- Locating of diesel/ petrol driven equipment
- Name and Signature of authorizing permit issuer, including the date, time of issue of the permit.
- Note: In situations where an excavation/trench is being dug to a depth >1 meter and wider > 0.5 meters or where the trench is being excavated for the purposes of conducting work on (installation repair) underground utilities/services a risk assessment must be performed before the excavation permit can be issued.
- Requirements of other FPEs must also be considered, e.g. confined spaces.
Risk
assessments performed on digging and excavation work must consider the
following and where identified assess the potential for injury or damage and
define the risk controls:
- Potential collapse of excavations or shoring
- Potential collapses of spoil heaps, adjacent structures or roads
- Potential for flooding from storm water, broken mains or ground water ingress
- Potential ventilation hazards from exhaust fumes from operating equipment
- Potential entrapments in confined spaces ( coffer dams, drains etc)
- Potential for inadvertent contact or damage to live services and underground tanks or structures
- Potential for workers being injured by falling objects, being struck by machinery or falling into the trench
- Potential for persons to fall into the excavation
- Emergency response requirements to recover personnel
Changes to the method of excavation or design of the excavation/trench including the angle of repose to slopes/protective support systems must be submitted to the excavation permit issuer before the change can be implemented (refer management)
4.2 Selection, Training, Competency and Authorisation
The
training and competency assessment system shall ensure competency standards
are established and applied for personnel designated as excavation permit
issuers. These competencies must incorporate the following functions:
- Identification and characteristics of soil types and ground conditions
- Identification of confined spaces
- Common hazard during excavation (atmosphere, water inrush, collapse, Cobile equipment etc)
- Protection methods
- Simple slope excavation
- Protective support systems (shoring, shielding, benching)
- Identification of underground utilities/ services
- Safety precautions when working or accessing underground utilities / services
Personnel designated as
authorized permit issuers must receive refresher training at period not
exceeding 3 years.
All personnel conducting risk
assessments in relation to digging and excavation work must:
![]() |
| Excavation Safety |
- Have completed excavation permit issuer training
- Have completed formal risk assessment training
An overview of the excavation permit requirements must be provided as part of the general induction program.
4.3 Communication and Awareness
Excavations/ trenches need to be identified by having a barrier erected around the perimeter of the area of excavation at a minimum distance of 2 meters from the edge of the opening.
Awareness
information and/or instruction must be provided on a regular basis to
personnel who may perform digging and excavation. The following topics
should be addressed:
- Definition of digging and excavation
- Hazards presented by excavations/trenches/ holes, openings
- Range of underground services installed at the operation
- Permitting requirements
- Means for inspecting protective support systems and access points
The design of excavations/
trenches must consider the soil type and the duration the excavation/ trench
will be left open. The application of either slope excavation or
protective support systems must address the following:
- Slope excavation
- Maximum slope angles for the various soil types
- Bench heights for the various soil types
- Protective support systems
- Trench shields are suitably designed for the expected compression load
- Screw jacks, wales, clingers, braces and sheeting (separate and continuous) are suitably spaced for the intended load
- Accumulated spoil from the excavation must not located closer than 2 meters from the edge of the excavation/trench
- Designated access and egress points are provided for personnel
- Segregation requirements are established where mobile equipment may operate or a loose digging face is present
In situations where water
accumulation is expected the following aspects must be considered within the
design of the excavation/trench:
- Requirements to prevent water accumulation from surface and ground water
- Dewatering pumps used are capable of dealing with, as a minimum, 25% above the expected accumulation rate
- Designated sump or drainage facility is provided for dewatering
Digging and excavation is only
permitted after written authorization is issued in the form of an excavation
permit. The person supervising the task must ensure the following aspects are
understood and applied by personnel involved in the task:
- Check the excavation/trench for tension cracks, surface water before permitting access to the area
- Erect barricading in the form of fencing/ barrier tape and signage around the perimeter of any open excavation/trench at a minimum distance of 2 meters from the edge of the opening.
- Personnel must use the designated access and egress points to an excavation or trench
- Personnel must not approach a loose digging face or mobile equipment excavating a trench
- Work involving repair to underground services/utilities, must have those services isolated and locked out before digging/excavation can commence (refer fatality prevention element for isolation and lockout)
- Diesel/ petrol driven equipment cannot be operated within a trench with personnel working. Atmospheric testing being performed prior to entry - (refer fatality prevention element confined space)
No requirement applies to this element
4.7 Emergency Controls
Where digging and excavation requires personnel to access the excavation/trench a specific rescue plan must be in place and suitable rescue equipment must be available before entry into the excavation/ trench is permitted.
4.8 Monitoring, Inspections and Audits
An inspection of excavations/ trenches must be performed weekly or when any of the following situations arise:
- Tension cracks, sloughing, undercutting, water seepage, bulging at the bottom, or other similar conditions occur
- After inclement weather (rainstorm)
- Change in the size, location, or placement of the spoil pile
- Any indication of change or movement in adjacent structures
- The inspection will be performed using a formal checklist and the findings recorded. Inspection checklist shall be retained for a period of 6 months.
Annual audits must be performed
to verify the quality and effectiveness of the requirements set out in this
element. As a minimum this will include :
- Schedules for audits
- Audit verification of:
- Quality of the risk assessments performed
- Quality of the inspection program for digging and excavations
- Compliance to training, competency, and awareness requirements
- Compliance to excavation permitting requirements
- Feedback and reporting requirements
Task/job observations must be
performed for the purpose of measuring compliance in regard to:
- Excavation permit issuing procedure
- Construction of protective support systems
- Work practices being performed within the trench/excavation
Processes must be in place for
the reporting, assessment, and correction of hazards identified with
equipment used for digging and protective support systems or trenching
practices and must address:
- Actions required to stand down unsafe equipment or stop work
- The recording of actions taken to correct the hazard or defect
5. Glossary of Terms
Accountability
The person designated to ensure that the assigned requirement is implemented. This person is held liable and answerable to the level of compliance against the stated requirement.
Authorised
![]() |
| Construction Safety |
Permission granted by the relevant Manager or nominee to carry out specific tasks.
Angle of Repose
Angle (or incline) from the horizontal surface at which the excavation wall is cut.
Competent Person
A person having a combination of training, education, experience, acquired knowledge and skills enabling them with the capability to perform specified tasks to a pre-determined quality, which may be assessed against, defined criteria.
Bench (benching)
Method of protecting employees from cave-in by excavating the sides of an excavation to form one or more horizontal levels or steps, usually separated by vertical or near-vertical surfaces.
Contractor
A firm or person employed under a contract to provide services to firm as distinct from a contract of employment.
Department Manager
The person nominated by the company as Manager under the organizational structure, also the most senior position within a firm contracting work to firm.
Excavation/ Trench
Man-made cut, cavity, trench or depression in the earth surface formed by the removal of soil and rock.
Personnel
Are all people including company employees, sub contractors, third party contractors and visitors which work within the firm managed operation and/or company employees which a performing work for the operation outside the lease area
Potential to cause a Fatality / Risk of a fatality
A hazard that has been identified that if not properly controlled will contribute to a fatal incident. This can be derived from previous fatal incident experience and /or having being identified by means of a risk assessment as having a consequence for fatal injuries.
Protective Support System
Method of protecting employees from cave-in, from material that could fall or roll from the face or wall into an excavation, or from collapse of adjacent structures. Protective support systems include support systems, sloping and benching, shields, and other devices or methods that provide necessary protection.
Sloping
Digging the sides at an incline away from the deepest part of an excavation to prevent cave-in. The angle required depends on factors such as soil type, environmental conditions (wet or dry soil), and equipment, structures, soil or other material near the edge of excavation.
Soil Type
Soils
are characterized by their physical properties and type - A, B or C.
- Type A -are cohesive soils with an unconfined compressive strength of 1.5 tons per square foot (144 kPa) or greater.
- Type B- are cohesive soils with an unconfined compressive strength greater than 0.5 tons per square foot (48 kPa) but less than 1.5 (144 kPa).
- Type C -are cohesive soils with an unconfined compressive strength of 0.5 tons per square foot (48kPa) or less.





No comments:
Post a Comment